ROBERT E. LEE AT FORT MACON
PART II
by:Paul Branch, Ranger/Historian at Fort
Macon State
Park.
(published in the Spring '03 Ramparts)
Editor’s note: The first part of this article was published in
the Fall 2002 issue of the Ramparts.
Lee’s inspection of Fort Macon was done with
great thoroughness. He took precise measurements of the lengths
and heights of the fort’s walls. He then went through each
casemate of the fort as well as outside buildings and structures noting
cracks, leaks and problems. While the overall condition of the
fort was good, there were a number of problems which needed to be
corrected, some of them quite serious. Lee studied each and
determined a solution.
First, settling of the foundation piers of the fort’s scarp wall
(the main wall of the inner citadel fronting the ditch) had resulted in
cracks running through the ceiling arch of each casemate. These
had to be sealed and patched with bricks and cement from below.
Then the earthen parapet had to be excavated on top of the fort to
allow access to the cracks from above on top of each casemate.
The cracks were then to be flooded with grout.
Next, Lee found all three of the fort’s magazines were very damp
and poorly ventilated. The wooden lining of each magazine was so
close to the masonry as to allow no air circulation between the
two. Each magazine was also secured by two solid oak doors which
likewise allowed no circulation when closed. To increase
ventilation he recommended a two-foot square passage be cut through a
wall of each magazine into the adjoining casemate to allow increased
air flow. The inner door of each magazine was to be replaced with
a grated door which would allow air circulation while providing proper
security for the magazine. Lee also recommended the wooden lining
of each magazine be replaced with a new wood lining which had a
one-foot spacing between it and the masonry walls of the magazine to
allow further air circulation.
Another problem Lee found involved the fort’s emergency water
system and cisterns. In operation, rainwater filtering through
the soil over each casemate flowed through a gutter in the bottom of
each casemate valley into an iron pipe in the fort’s parade wall. The
pipe ran laterally through the wall over the doors and windows to a
point above each cistern, located under the parade walkways. The
water was then conveyed down by a single downspout in the wall to each
cistern. The iron pipe had proved inadequate for the amount of water
and clogged easily. Water then backed up in the casemate valleys
and leaked below into the casemates. What water did reach the cisterns
became brackish and undrinkable.
Lee’s solution was to get the water from above the casemates to
ground level as quickly as possible so that it had little chance to
leak into the casemates. Dispensing with the iron pipe, he called for a
gutter chase to be chiseled in the parade wall from the head of each
casemate valley to the foot of the wall. Each was to receive an
8-inch diameter zinc downspout to bring the water down from the
casemate valleys. At the foot of the parade wall, under the
walkway, the downspouts would tie into a covered gutter which would
then convey the water along the wall to the cisterns.
To stop the salty tidal groundwater from contaminating the
cisterns themselves, Lee ordered the cistern interiors to be coated
with hydraulic mortar and built up with one course of bricks.
When he examined the four counterfire galleries under the fort’s
outer wall, Lee found two problems. These rooms were
designed to defend the ditch (the sunken area between the fort’s outer
and inner walls) against assault. First, the rooms were full of
water several feet deep which he thought had percolated through the
wall from the ditch. Second, though the galleries were loopholed
for riflemen to shoot from, he felt their firepower was inadequate to
stop an assault.
To control the amount of tidal water entering the ditch, Lee
called for a sluice gate to be installed in the culvert which conveyed
the water into the ditch from the creek outside the fort.
Controlling the water in the ditch should control the water leaking
into the counterfire galleries.
To increase the firepower of the galleries in defending against
an assault, Lee proposed to install a total of six carronade cannons in
the three largest galleries from which a sweeping fire was possible.
Carronades were stubby, large caliber naval cannons frequently utilized
in forts for interior defense to deliver a sweeping, scattering fire
with anti-personnel ammunition.
Should the fort have been called upon to fight, Lee found only a
limited potential for defense at hand. It had received only a
third of its intended armament and had only one hot shot furnace inside
the citadel for use against naval attack. No guns were mounted
and, had there been a need to, there were no permanent gun mounts in
the fort. Fourteen temporary gun mounts, consisting of wooden
platforms and traverse circles, all mounted on brick foundations, had
been installed four years earlier but these were insufficient for
proper defense. Lee’s recommendation was that permanent brick and stone
gun mounts be built for the fort’s full intended armament. Also,
a second hot shot furnace was needed to serve the guns on the fort’s
outer wall against naval attack.
These repairs covered all the fort’s major problems. Added to
these were also a few minor items. Lee completed his inspection
of the fort and its site by December 9, 1840. Although the
weather was still poor, he sent a letter that day to the Engineer
Department advising of his intention to continue on to Fort Caswell
(Southport, N.C.) and Fort Moultrie (Charleston) to observe the
breakwaters previously constructed at those two forts. Because
the beach at Fort Macon required immediate attention, he planned to
obtain information on the cost of the breakwaters and see how they
could be adapted to the erosion situation at Fort Macon.
It is not known with certainty if Lee did continue on to observe
the erosion control efforts at Forts Caswell and Moultrie as
planned. He did not inspect either of the forts themselves or
write any report of going there. However, it is clear from his
December 9 letter that he regarded the immediate halting of the erosion
at Fort Macon as critical and that studying the breakwaters at Caswell
and Moultrie would aid in his recommendations for Fort Macon’s
problems. He could’ve easily made the trip to each of these forts
by steamer in just a few days.
It is certain that Lee was back with his family at Arlington,
Virginia, for the holidays. At the beginning of 1841 he sat down
with his field notes to draft his final report to the Engineer
Department on his findings and recommendations in regard to Fort
Macon. His 6-page “Report on the site of Fort Macon, N.C.” with
its accompanying estimates for constructing two permanent stone jetties
was penned on January 7, 1841. He recommended the two jetties
each be a minimum of fifty yards long to be effective, They would
require a total of 6380 linear feet of palmetto logs and 3630 tons of
stone, for an estimated cost of $25,000. This would provide
immediate protection to the fort. To permanently secure the fort
site Lee stated in a further 6-page report on February 22, 1841, that
the jetties had to be much larger: 200 yards long for Jetty 1 and 100
yards long for Jetty 2. Carrying them to this extent would
require 22,535 feet of palmetto logs and 8317 tons of stone. The
cost of full length jetties, along with brush fences to stabilize the
dunes west of the fort, was $70,000. Lee also drafted two
detailed maps of the site of Fort Macon dated January 7 and February
22, 1841, showing the locations and details of his two proposed jetties.
As for repairs to the fort itself, Lee’s 22-page “Report on the
State and Condition of Fort Macon, N.C.” with estimates for repairs was
completed on January 22, 1841. It is one of the most detailed
inspections of the fort ever conducted. In carefully calculating
the costs for materials and labor, Lee’s estimate for all the repairs
to the fort amounted to $17,674.
This completed Lee’s work at Fort Macon. Although he had
the choice of returning to the Carolinas to take charge of the repairs
and improvements to Fort Macon and the other forts there, he decided
instead to take a new, perm up, his reports served as the blueprint for
other engineers to do so. In June, 1841, another engineer was
assigned to carry the recommendations into effect. The
recommendations were to initiate a phase of repairs and alterations to
the fort and its site which lasted from 1841 to 1846.
The recommendations for Lee’s two jetties were adopted and four
others were even added to provide additional protection. They
stabilized the fort site for years. All are currently covered
over with sand. The large sea jetty present today was built over Lee’s
Jetty 1.
The repairs to the fort were also carried out during the 1841-46
period. These, along with additional repairs and alterations
added by the Engineer Department, brought Fort Macon to a pinnacle of
top military condition and readiness before the outbreak of the War
Between the States. In that conflict, both Robert E. Lee and Fort
Macon would receive their trial by fire..
Return
to Fort Macon Ramparts Web Page